LD-Vera Lou (1).jpg
SentralHomes-Logo_-01.png

Construction Updates

Construction Updates

4215 Elmwood St

  • Lot cleared

  • Foundation prep

20201021_123241.jpg
20201021_123535.jpg

4215 Elmwood St

  • Foundation forms set

  • Scheduled for survey

20210426_142956.jpg
20210426_143014.jpg
20210506_124758.jpg
20210510_103039.jpg

4215 Elmwood St

  • Framing has started.

Planned construction activity

  • Sheathing

  • Decking / Cornice

  • Finished Roof

  • Windows Exterior Doors

4215 Elmwood St

  • Framing completed.

  • Sheathing completed

  • Decking / Cornice completed

  • Finished Roof completed

  • Windows Exterior Doors completed

  • Plumbing rough completed

  • Electrical rough completed

Planned construction activity

  • HVAC

  • Insulation

  • Drywall hang

  • Tape and float drywall

  • Texture drywall

Infrastructure

Water and sewer city tap

4215 Elmwood St

  • Framing completed.

  • Sheathing completed

  • Decking / Cornice completed

  • Finished Roof completed

  • Windows Exterior Doors completed

  • Plumbing rough completed

  • Electrical rough completed

  • HVAC

  • Insulation

  • Drywall hang

Planned construction activity

  • Tape and float drywall

  • Texture drywall

  • doors and trim

  • Interior paint

  • Exterior paint

Infrastructure

Water and sewer city tap